Dig shovel width trenches along the external wall of the building exposing
the foundation wall surfaces 50cm deep holes, all along this trench and
pour chemical emulsion.
Treat the back fill earth with chemical emulsion to the trench directing
the spry towards the wall surface. If there is a concrete or masonry apron
around the building, drill 12mm holes as close as possible to the plinth
wall and pump chemical emulsion to soak the soil linear meter..
B) Internal treatment
WOOD WORK TREATMENT
The existing wooden fixtures in the building, which are in contact
with the floor or the walls and which are infested by the termites
will be treated by drilling 6 mm at an angle of 45 degrees at the
junction of wood work and masonry and squirting the chemical emulsion
in the holes till refusal or to a maximum of half liter per hole.